Mayville Wastewater Lagoon Improvements
Spicer Group was hired by the Village of Mayville to provide professional engineering services for the design and construction improvements to the wastewater lagoon system. Phase I of the project included construction of a third lagoon cell with a dual liner system and rip rap side slope protection, and transfer structures. Spicer Group also assisted with the USDA Rural Development financial application process and construction administration, design and permitting for approximately 1,000 feet of sewer replacement, 4,600 feet of CIPP sewer lining, replacement of two existing drypit pump stations with submersible style stations, and rehabilitation of a third drypit pump station.
Phase II of this project is still ongoing but has included design, permitting, and construction administration for the rehabilitation and extensive improvements to the two existing lagoon cells at the wastewater lagoon system.
The project has received a $9.9M grant and $4.5M loan for the project, through the USDA Rural Development, which was the largest program grant award in the nation for the year of 2024.