M90 Croswell Bridge

Spicer Group provided full-time inspection and material testing services to the MDOT Huron TSC for the replacement of M-90 over the Black River and Mills Creek. This project included the complete removal of the existing structure and construction of a new 3-span bridge with 36 inch prestressed concrete I-beams.

  • Full removal of the existing structure because it was old, at the end of it’s life cycle

  • Contaminated soils